Shipment of 909-tonne Intervention Tower from Middlesbrough to Singapore

This is a story of a tailored engineered solution developed together with the client’s engineering team and led by the engineering team of Bertling Logistics. With the great teamwork of all parties involved, Bertling Logistics' in-house technical engineering team in Middlesbrough in close collaboration with our project logistics team in Singapore delivered a safe, practical, cost-effective heavy-lift transport solution.

POL: Middlesbrough, UK
POD: Singapore
Industry: Oil & Gas
Dimensions: 1,000Te and over 40m high
Bertling Team: Middlesbrough & Singapore

This is a story of a tailored engineered solution developed together with the client’s engineering team and led by the engineering team of Bertling Logistics. With the great teamwork of all parties involved, Bertling Logistics delivered a safe, practical, cost-effective heavy-lift transport solution.

In the autumn of 2019, Bertling Logistics started with the client FTAI Ocean to discuss the transportation of the Intervention Tower in the north of England. This new Smart Tower System will facilitate integrated riser-less and riser-based well intervention operations on FTAI Ocean's flagship DP3 Well Intervention Vessel the PRIDE. The developed solution was to transport the massive tower from UK to Singapore for installation onto the PRIDE. To find the best technical and commercial solution, Bertling Logistics performed a study for all possible shipment modes, including heavy lift vessels, gearless vessels with shore/floating cranes, and ro-ro vessels.

The Tower was located at Port Clarence on the river Tees in Middlesbrough, near the home of Bertling Logistics’ Heavy-Lift and Engineering Team. The two known operational limitations for the location were available draught alongside the yard and a headroom restriction downstream in the form of the historic Tees Transporter Bridge. Addressing these two issues: to pass under the bridge, the Tower had to be stowed inside the hull of the HL vessel, and to mitigate the draught issue, the Tower would need to be “lightered” by barge across the river alongside the HL vessel where much deeper draught was available at the Port of Middlesbrough.

Bertling Logistics advised the best method of jacking the Tower up to SPMT height, a challenging task for a structure of almost 1,000Te and over 40m high. 4 x 500Te capacity perpetual climbing jacks were proposed, and Bertling Logistics provided design assistance to allow the retrofitting of the required jacking lugs that would ultimately allow the insertion of the SPMT’s beneath the Tower to allow it to be site moved to the quay edge. The selected vessel type had an open dock hull arrangement. Although width-restricted in the hold by the aft vessel crane, a stowage plan was agreed upon.

During discussions between Bertling Logistics and the Harbour Master, safe passage under the Transporter Bridge at a certain tide height was confirmed as feasible and suitable draught and tidal curves were confirmed to be available during neap tides on six days per calendar month. Additional OOG cargo had been added to the scope of Bertling, which include the transportation to their Middlesbrough base and stowage of general cargo into 20 x SOC’s as well as loading 5 x items of additional OOG cargo.

On 18 October 2022, the OOG cargo was loaded using the vessel’s gear alongside the berth at Port Clarence, and the vessel laid by at Port of Middlesbrough overnight. On 19 October 2022, the Tower was ro-ro loaded to the vessel, and following 10% securing having been applied to the Tower, the vessel relocated to the Port of Middlesbrough to complete sea fastening and load the containerised cargo.

On the evening of 22 October 22, the vessel sailed, passing under the Transporter Bridge with just over 1.0m clearance. Due to the height of the tower close monitoring of the sea passages and weather routing have been required to keep the acceleration forces in with the design parameters of the tower. 

Following passage via the Suez Canal, the Indian Ocean, and the strait of Malacca, it arrived in Singapore on 20 November 2022 after 28 days of ocean passage. In preparation for the loadout, the Singapore-based engineering team from Bertling Logistics prepared the required installation of an elevated ramp on the shipyard quay and spacer barges to mitigate the limited draught at the receiving jetty. On 24 November 2022, the Tower was successfully reloaded onto SPMT trailers and rolled out of the vessel on the yard.

The transportation project was successfully completed because of careful planning and cooperation between Bertling Logistics’ Heavy-Lift & Engineering Team and key first-class subcontractors.